Our Ground-Breaking ceremony took place right after the Sunday service on May 24.
Folks brought festive things like flutes and ribbons and flowers in your hair!
Construction Timeline Highlights
Estimated Completion Dates
-
Construction Staging and Mobilization
..Tue June 2, 2009
-
Demolish kitchen and rough in plumbing
..Fri June 5, 2009
-
Move or demolish existing house
..Thu June 11, 2009
-
Excavation and site grading
.Thu June 18, 2009
-
Plumbing and underground electrical
.Tue July 14, 2009
-
Pour basement slab
..Fri July 17, 2009
-
Windows and Exterior Doors Installed
.Fri Sep 11, 2009
-
Roof Completed
..Thu Sept 24, 2009
-
Framing Completed
..Thu Sep 24, 2009
-
Rough Landscaping and sidewalks
..Fri Oct 2, 2009
-
Siding, exterior trim and gutters
Tue Oct 20, 2009
-
Sheetrock and texturing
..Tue Nov 10, 2009
-
Open up and tie into existing building
Wed Nov 18, 2009
-
Merry Xmas and Happy New Year
-
Flooring
.Fri Jan 15, 2010
-
Plumbing Finish and Trim
.Mon Feb 15, 2010
-
Complete Landscaping
..Tue Mar 2, 2010
-
Final Inspections
.Tue Mar 16, 2010
Timeline - This chart is NOT official - just a general illustrative scheme!:
|